# Texas data-center grid requests reach 474 GW amid scrutiny of speculative demand

_Tuesday, September 1, 2026 at 8:25 AM EDT · Infrastructure · Latest · Tier 1 — Major_

![Texas data-center grid requests reach 474 GW amid scrutiny of speculative demand — Primary](https://media.thenextweb.com/2026/09/US-data-center.jpg)

Texas has 474 GW of data-center connection requests in its grid queue, more than five times the state's record peak demand, according to a Reuters analysis cited by The Next Web. The state ordered an audit in early August covering project ownership, tax incentives, water use and power-generation plans. The report says developers can file requests for several possible sites at relatively low cost, leaving grid planners unable to determine how much proposed demand will be built.